16 hours ago, Leo91 said:

I was just thinking. Depending on the delay do the club have to go through building permission again. This was a serious proposal, who knows how much was spent in this endeavour. Wouldn't surprise me if everything was scraped.

Three years from date of grant, which was March 2017. This is here:

https://www.lbhf.gov.uk/sites/default/files/section_attachments/stamfordbridge_final_decision_letter_310317.pdf

Share this post


Link to post
Share on other sites

It will usually say 'Development to begin within three years of date of this permission' or something similar. That means you can dig a small hole and get the building inspector to come and look at the foundations of the burger stand, he will then lodge that he has been and building work has commenced, thus the planning is instigated. That is how it works for home owners and small developers anyway, I'm sure this would draw more attention. I am actually surprised it is only 3 years, for bigger developments it is usually longer to recognise the time it takes to tender and prepare the works.

I read reports over the weekend that Roan with some other Oligarchs were on a list being targeted for disruption by the UK Govt and hoping to get the US and other countries to sign up to it. I feel we are headed towards a sale in the next couple of years, not that I think Roman particularly wants to but will be pushed into it.

Share this post


Link to post
Share on other sites
Flinkers   
22 hours ago, Sciatika said:

Extrapolated from the Time Limits section of the permission:-

  1. Commencment of site preparation to be no later than 31 March 2020.
  2. Start of Demolition no later than 31 March 2022.
  3. Start of Main Construction no later than 31 March 2023.

Miss any of those dates (without an Extension) and planning permission is rescinded.

Share this post


Link to post
Share on other sites
paulw66   
3 minutes ago, Flinkers said:

Extrapolated from the Time Limits section of the permission:-

  1. Commencment of site preparation to be no later than 31 March 2020.
  2. Start of Demolition no later than 31 March 2022.
  3. Start of Main Construction no later than 31 March 2023.

Miss any of those dates (without an Extension) and planning permission is rescinded.

Interesting, thanks, 

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now